PLANS to carry out track improvement and platform extension work will see the railway line between Barnstaple and Crediton closed for nine days from tomorrow, Saturday, April 10.

From tomorrow until Sunday, April 18, buses will replace trains between Barnstaple and Crediton.

Buses will be timed to connect with trains which will continue to run between Crediton and Exeter.

A separate shuttle bus will serve Yeoford, connecting with trains at Crediton.

The bus services will travel via the Crediton Link Road during the daytime road closure in Exeter Road, Crediton, which is in place now and is expected to be in place until April 16.

WALL COLLAPSE REPAIR

However, there is good news that repairs to the collapsed wall in Exeter Road will also go ahead during the Exeter Road daytime closure by Western Power Distribution for cabling works.

It is hoped that this wall repair will not affect the work being done by Western Power and delay the timing of it re-opening.

County Councillor Nick Way has asked that Devon County Council check if a proper consultation about the timing of the road and rail closures at the same time had been carried out, including contacting the bus companies and Network Rail.

RAIL UPGRADES

As part of these rail improvements, Network Rail will be working day and night on a number of important upgrades.

At Lapford and Kings Nympton stations engineers will be working to renew the ballast that supports the track, whilst at Eggesford station platforms one and two will be extended and new lighting, drainage and fencing will be installed.

There will also be a range of work to a number of bridges on the Tarka Line.

At Penstone repairs are being made to the under bridge, including replacing the existing wrought–iron deck with a new standard steel deck.

Near Coleford the track and bridge at Battesford is being removed and then infilled.

At Waterleat Underbridge near Yeoford engineers will remove the track, carrying out steelwork repairs, grit blasting, painting and waterproofing the bridge.

GWR Station Manager for the branch line, Melanie Harvey, thanked passengers in advance for their patience and reminded them of the changes ahead which these improvement works are helping to bring.

Melanie said: “This work is important to ensure that we can continue to provide services people can rely on at this time, and we thank customers for their patience in advance.

“We have been working hard to make sure that people can be confident to travel safely, and that includes running as many trains and carriages as we can to make extra room, and replacement buses where trains cannot operate, as well as enhanced cleaning and social distancing measures.”

LINE SPEED INCREASE

Completion of the work will allow trains to run at an increased line speed, providing greater resilience, say GWR.

Platform extension work being carried out at Eggesford will also make boarding or leaving the train easier and improve accessibility for less-abled customers.

These improvements come after a major timetable change was introduced on the Tarka Line in December 2019, which brought a more consistent and frequent service pattern throughout the day.

With the Government’s present advice restricting travel, GWR is operating a reduced timetable. Customers should follow Government guidelines, people should continue to work from home where they can and minimise the number of journeys they make where possible, avoiding travel at the busiest times. Find out more at: gwr.com/safety .

The train operator has been providing rail services throughout the pandemic and has worked to ensure these are as safe as possible.

This includes increased cleaning regimes and the use of a virucidal spray; extra staff at key stations to offer help and guidance; and processes in place to help customers maintain a safe distance where possible, such as restricting the number of reservations available.   

For further travel advice and information on the work please visit: GWR.com/Barnstaple .